Huaneng Group connected a dual-flywheel frequency regulation system to the grid at its Lanzhou combined heat and power plant on 6 November. The connection closed out a commissioning process of roughly a year that the group says validates large-scale flywheel storage for coal-fired generation assets.
The system pairs two flywheel units with a combined rating of 5.5 MW and 1.375 MWh. The primary unit is a 5 MW, 1.25 MWh flywheel that spins at up to 3,200 rpm on five-axis active magnetic levitation; Huaneng claims it is the highest-power single flywheel unit in China. A secondary 0.5 MW, 125 kWh inertia flywheel handles smaller frequency deviations alongside it.
Huaneng says the paired design reaches a grid response time below 100 milliseconds and a regulation accuracy above 99.5%. The company attributes these figures to proprietary control integration with the plant's distributed control system. The performance figures have not been independently verified.
Flywheel storage is designed for speed rather than bulk energy delivery, since 1.375 MWh is a small buffer. A lithium battery frequency regulation system typically responds in a few hundred milliseconds; the flywheel array's sub-100-millisecond response is described as letting the thermal unit react to grid disturbances faster than its own mechanical inertia would normally permit. The 5 MW primary flywheel handles large frequency excursions, while the smaller unit manages finer, continuous corrections that would otherwise wear down the larger machine.
Technical development was led by the Xi'an Thermal Power Research Institute, Huaneng's internal R&D arm. Equipment installation and the mandatory 168-hour continuous trial run were completed in December 2025, and the system then operated under monitored conditions before the formal commercial grid connection.
The Lanzhou plant sits in Gansu province, a core zone of northwest China's wind and solar buildout. Grids in the region have faced persistent frequency stability challenges as variable renewable capacity has grown faster than conventional dispatchable generation. Under China's two-part ancillary services assessment rules, grid operators assess financial penalties when frequency response falls short of benchmarks. Huaneng's stated rationale for the investment is partly to reduce those penalty costs while earning ancillary services revenue.
Flywheel storage carries structural advantages for this role: no chemical degradation, a claimed cycle life of tens of millions of charge-discharge cycles, and no fire risk. It remains more capital-intensive per megawatt than lithium battery alternatives at current prices. Whether the dual-flywheel architecture proves economically replicable across other thermal plants will depend on how the ancillary services market values millisecond-range response.
Key facts
- 5.5 MW combined rating of the two flywheel units
- 1.375 MWh combined storage capacity
- Primary flywheel: 5 MW, 1.25 MWh, up to 3,200 rpm on five-axis active magnetic levitation
- Secondary inertia flywheel: 0.5 MW, 125 kWh
- Claimed grid response time below 100 milliseconds, not independently verified
- 168-hour continuous trial run completed in December 2025
Sources
- Huaneng commissions dual-flywheel frequency regulation system, claims China single-unit power record — pv magazine
Other news outlets are named as sources but not linked.
Discussion
Technical questions and corrections are welcome. Comments are signed and checked before they appear.
No comments yet.
Sign in to add a typed review comment. Reviews are signed with your name.